Emergency Generator Replacement in 14 Days: A 350 kW Standby Diesel for a Sarasota Condominium
SPVD-3500 · 350 kW VOLVO-POWERED STANDBY DIESEL GENERATOR
What Happens When a New Condominium Fails Its Generator Inspection?
How Gillette Replaced the Generator in 14 Days
Project Summary
Gillette replaced a failed standby generator at Peninsula Residences, a newly constructed condominium in Sarasota, Florida, in 14 days. The SPVD-3500, a 350 kW Volvo-powered standby diesel generator, was built in seven days and installed and load bank tested on site fourteen days after the first call. The building passed inspection within days, and occupancy proceeded on schedule.
Sarasota Condominium Generator Replacement: Project Overview
An urgent turnaround on a 350 kW standby generator for Peninsula Residences, a newly constructed condominium in Sarasota, Florida, developed by Sam Gault of The Gault Companies. The building’s original generator had been specified incorrectly and did not meet the required output, and it failed inspection with the county just as residents were preparing to move-in, with occupancy for a fully pre-sold building on the line. Gillette built the replacement SPVD-3500 Volvo-powered standby diesel generator, with a Stamford generator end, in seven days. Fourteen days after the first call, it was on site, installed, and load bank tested.
Peninsula Residences · Sarasota, FL
Why Did the Original Generator Fail Inspection?
ON SITE in SARASOTA, FL
CRANED INTO PLACE, 14 DAYS FROM FIRST CALL.
The replacement SPVD-3500 arrived by truck from Indiana and was lifted into position at Peninsula Residences the same week.
There were several factors that made Gillette the right choice:
01
Emergency Generator Production: Built in Seven Days
Gillette was contacted on a Monday with the corrected specification. An estimate was approved the same day. The unit was built in seven days, then shipped directly from the Indiana facility to Sarasota, Florida. Fourteen days after that first call, the generator was installed and load bank tested on site.
02
A Dealer Relationship Built Over Two Decades
The dealer, Steven Jamison, of Critical Diesel Energy Systems, who handled this project has worked with Gillette since 2005 and did not consider any other manufacturer for this replacement. That standing relationship, and Gillette’s willingness to expedite a custom-built unit on short notice, meant the dealer made one call and got a firm answer the same day.
What Gillette Built?
- SPVD-3500 standby diesel generator
- 350 kW standby output
- Volvo engine
- Stamford generator end
- Built in seven days and shipped from Gillette’s Indiana facility
- Load bank tested on site roughly 24 hours after it was craned into place
What the Dealer Says About Gillette
We found a perfect partner in Gillette Generators. They show up for you especially when you have customers in a bind. Highly trustworthy and extremely professional quality partners like this simply don’t exist any more.
STEVEN JAMISON, CRITICAL DIESEL ENERGY SYSTEMS, INC
The Result: Inspection Passed, Occupancy on Schedule
Once the replacement unit arrived, the old generator was removed and the new one craned into place, with load bank testing completed roughly 24 hours later. The building passed inspection within days, and occupancy proceeded on schedule for the holidays.
Ready When Readiness Matters.
What This Means for Dealers, Contractors, and Building Owners
When a generator fails inspection, the move-in date does not wait. On this project the dealer made one call, got a firm answer the same day, and had a replacement installed and load bank tested fourteen days later. We quote delivery in weeks. They quote in months. Lead times vary by project and configuration. Contact the factory for a current timeline on your specific application.
Frequently Asked Questions
How fast can Gillette replace a failed generator?
Why would a new building's generator fail inspection?
What generator did Gillette supply for the Sarasota condominium?
An SPVD-3500: a 350 kW Volvo-powered standby diesel generator with a Stamford generator end, built in seven days and shipped from Gillette’s Indiana facility.
Facing a Failed Inspection or a Deadline That Can't Move?
Call the factory. We quote delivery in weeks. They quote in months. Lead times vary by project and configuration. Contact the factory for a current timeline on your specific application.