Ready When Readiness Matters /
574.264.9639
Gillette Generators
Gillette SPVD-5000 500 kW Volvo-powered standby diesel generator for a Long Island City, Queens hotel
Home » Hospitality » 500 kW Hotel Generator, Long Island City, NY
CASE STUDY
LONG ISLAND CITY, NY

500 kW Standby Diesel Generator for a Long Island City Hotel, On Site in 4 Weeks

SPVD-5000 · 500 kW VOLVO-POWERED STANDBY DIESEL GENERATOR

What Happens When a Hotel Needs a 500 kW Generator Fast?

Gillette needed to set up and deliver a large 500 kW standby diesel generator.

The Generator: Volvo-Powered SPVD-5000

SPVD-5000 Volvo powered standby diesel generator to fit the need.

500 kW
STANDBY DIESEL OUTPUT
4WKS
CONCEPT TO ON-SITE
4BRKR
FACTORY-INSTALLED BREAKERS
VOLVO
POWERED · SPVD-5000

Project Summary

After a last-minute size change, Gillette delivered an SPVD-5000, a 500 kW Volvo-powered standby diesel generator, to a high-rise hotel in Long Island City, Queens, NY, on site in 4 weeks. All 4 breakers feeding the building’s emergency sub-feed panels were installed at the factory, in a very tight space where most vendors pass on these types of installations.

Long Island City Hotel Generator: Project Overview

This was an urgent need for a quick turn-around on a 500 kW Standby diesel generator, Our SPVD-5000 Volvo powered standby diesel generator fit the need. The project was for a high-rise hotel installation in Long Island City, Queens, NY.

High-Rise Hotel · Long Island City, Queens NY

What Happens When a Generator Size Changes at the Last Minute?

The dilemma was the customer had a last-minute size change to the generator for this project. Gillette reacted immediately going to work to meet the project’s deadline of having the generator on site in 4 weeks.

There were several factors that again made Gillette the right choice.

01

On Site in 4 Weeks

Customer needed the generator on site in 4 weeks. Gillette was able to step up and deliver.

02

Four Factory-Installed Breakers in a Tight Space

Another requirement was the need for 4 separate breakers to be installed to accommodate the various sub-feed panels for the building’s emergency backup needs. Gillette met that challenge by providing an engineered solution to ensure all 4 breakers were installed at the factory which is a very challenging endeavor due to the fabrication involved to ensure proper form, fit and function in a very tight space, where most vendors pass on these types of installations, Gillette’s dedicated team of engineers and production staff are more than willing to take on these types of challenging builds and delivery deadlines with no hesitation.

03

A Formal Acceptance Test Protocol at Every Site

Every installation is accepted under a Michigan State Police ATP: serial number capture, in-field testing, alarm verification, and signal confirmation back to the network operations center. No site is handed over until the state’s own representatives sign off.

What Gillette Built?

  • SPVD-5000 standby diesel generator
  • 500 kW standby output
  • Volvo engine
  • 4 separate breakers installed at the factory for the building’s emergency sub-feed panels
  • On site 4 weeks from concept

The Result: A 500 kW Generator on a 4-Week Deadline

The overall project was a great success, Once again proving that Gillette Generators is here to meet the needs of our dealer/customers on a daily basis. Providing solutions for your difficult installations and timelines when possible.

What This Means for Your Project

A last-minute size change, factory-installed breakers in a very tight space, and a 4-week deadline are the kinds of builds most vendors pass on. Gillette takes them on. We quote delivery in weeks. They quote in months. Lead times vary by project and configuration. Contact the factory for a current timeline on your specific application.

Frequently Asked Questions

Can Gillette deliver a 500 kW standby generator in 4 weeks?

On the Long Island City hotel project, Gillette had a 500 kW SPVD-5000 standby diesel generator on site in 4 weeks, after a last-minute size change. Lead times vary by project and configuration, so contact the factory for a current timeline on your specific application.

Why install generator breakers at the factory?

On the Long Island City project, the building needed 4 separate breakers to accommodate the sub-feed panels for its emergency backup needs. Gillette installed all 4 at the factory, where the fabrication could ensure proper form, fit and function in a very tight space.

What engine powers the Gillette SPVD-5000?

Volvo. The SPVD-5000 is a 500 kW Volvo-powered standby diesel generator built by Gillette Generators.

99%
ON-TIME DELIVERY
UL2200
CERTIFIED
60+
YEARS IN INDIANA
Weeks
NOT MONTHS

Did Your Generator Spec Just Change?

Call the factory. We quote delivery in weeks. They quote in months. Lead times vary by project and configuration. Contact the factory for a current timeline on your specific application.

Ready when readiness matters.

Gillette Generators